Monday, September 12, 2011

Back Online



Since the disaster with the drains and the plumbing and the rapid house move (or should that be 'bungalow move'?) we've been without internet connection for over three weeks, during which time the renovation has moved on considerably and I've driven myself to distraction trying to look for bathroom taps on Dr B's i-Phone (no, I don't have an i-Phone, I have an old fashioned version that only rings 2.5 times before cutting off and not even the shop can figure out why).


We're now at the beginning of week 6 and the ground floor brick and blockwork was finished about a week ago, though things were then held up due to the late delivery of the steelwork (which cost us an extra £2,500 since the structural engineer has apparently over-engineered the building such that it can now take the weight of a multi-storey car park - reassuring I suppose, but I'd already mentally spent that money on a Multi-York sofa).


And then they waited for the scaffolding and as of last Friday, we were waiting for 'more scaffolding' to help them reach the highest brickwork and to provide access for the roofer. You'll see from the photograph that the front of the build now proudly displays two new window openings (bathroom to the left, en-suite to the right) as well as new windows to the existing building, which completes the replacement of all windows on the front elevation and marks the beginning of that horrible cedarwood cladding being ripped off (hurrah!).


No comments:

Post a Comment